MPStormwater

Stormwater Management

Northgate Way

AAC N 105th and Northgate Way TIB- February 2012 to December 2012

MP Stormwater Engineering designed the detention pipes and water quality facilities for this SDOT 1.4 mile paving project that lies within the Piper’s Creek, Densmore and Thornton Creek drainage basins. MGSFlood models were developed for each detention pipe, Filterra, and Stormfilter units. Offsite basin analysis completed for a natural drainage way discharging to the project limits. The inclusion of new storm drain with the existing system required conveyance, inlet, and gutter calculations.

Waterfront

Waterfront Seattle Project – Feb 2013 to present

The continuous waterfront includes new surface streets along with pedestrian and bicyclist improvements. MP Stormwater was responsible for modeling the stormwater conveyance design, flow control and water quality facilities on the numerous individual projects that will accomplish the Seattle waterfront vision. The Alaskan Way and Elliott Way projects include new public storm drains that MP Stormwater used StormCad to model and MGSFlood to design stormwater facilities.

SR16_I5

I5-SR16 QC Design Build- August 2016-March 2017

QC role for stormwater management and design for final stages of project.

Top